Yazeed Alotaibi Project management

Estimation · three-point PERT

An estimate is a range, not a number.

Break the work down, give each task an optimistic, likely, and pessimistic figure, and this rolls the whole thing up — expected duration and cost, with the confidence interval around them. Deviations combine in quadrature, which is the part most spreadsheets get wrong.

Project total 0 tasks
E = (O + 4M + P) ÷ 6 σ = (P − O) ÷ 6 σ total = √(Σσ²)
Duration
days
Cost
Confidence

The band is the confidence interval. The ticks are the absolute best and worst case — every task at its optimistic figure, then every task at its pessimistic one.

Work breakdown

Optimistic · most likely · pessimistic, per task

Rolled-up deviation assumes tasks vary independently. Where the same risk drives several tasks — one vendor, one scarce specialist, one permit — the real spread is wider than this shows. Treat the band as a floor on your uncertainty, not a ceiling.